Flat Cancellation by Builder Without an OC? UP RERA Says “Restore the Flat, Pay for the Delay” [Read Order]

Imagine paying almost the entire price of your flat, waiting years past the promised date, and then receiving a letter that says your booking stands cancelled — because you did not “come forward” to take possession of a home that the law did not yet permit anyone to occupy. For several Greater Noida homebuyers, that was not a hypothetical. It was their reality, until the Uttar Pradesh Real Estate Regulatory Authority (UP RERA) stepped in.
In a recent common judgment passed under Section 31 read with Section 37 of the Real Estate (Regulation and Development) Act, 2016 (“RERA Act”), Hearing Bench-1 of UP RERA, presided over by the Hon’ble Chairman, decided a batch of homebuyer complaints against a single promoter. The ruling sends a clear message on possession without an occupancy certificate: a builder cannot dress up an “offer of fit-out” as an offer of possession, raise demands on it, and then punish buyers for not complying. Our firm represented one set of complainants in the batch (Complaint No. 3), with arguments advanced by Adv. Utkarsh Shubham.

The Dispute at a Glance
The complaints arose from the same housing project and raised identical grievances, so the Bench heard them together and decided them by one order. The buyers sought legal physical possession with a valid occupancy/completion certificate (OC/CC), interest for the delayed period, and execution of the conveyance deed.
The promoter’s defence was familiar to anyone who follows real estate litigation. It claimed that the project was slowed by pollution-control construction bans and COVID-19; that it had obtained the fire, lift, electrical and other NOCs and applied for an OC, entitling it to a “deemed” OC; that it had issued offers of fit-out, demand letters, reminders and a final call; and that since buyers did not pay or turn up, the units were cancelled. It even asked the Authority to permit forfeiture of a substantial portion of the price as earnest money.
So the real question was simple: can an "offer for fit-out" and a subsequent unilateral flat cancellation by the builder survive when the builder never had a lawful occupancy certificate to begin with?
What UP RERA Held on Offer of Possession Without OC and Subsequent Flat Cancellation by Builder
1. A “Deemed OC” Has to Be Proved; It Cannot Simply Be Claimed
The Authority turned to Regulations 22 and 23 of the Greater Noida Industrial Development Area Building Regulations, 1992. A building cannot be occupied until the occupancy certificate is issued. The only exception is in the proviso: if the CEO neither issues the certificate nor communicates an inability to do so within 30 days of receiving the completion notice, the building may be occupied, but only after the owner sends an intimation to the Authority.
The promoter had to prove a complete application backed by all required NOCs, the expiry of 30 days, and the intimation to the Authority. It filed neither the four NOCs nor a copy of its claimed OC application. The Authority found that application neither complete nor lawful. It also noted that the UP RERA office order on deemed OC/CC that the promoter relied upon (dated 16.09.2019) had been revised by a fresh office order dated 14.06.2021.
2. No OC Means No Valid Offer of Possession, and No Valid Demand
The Authority read together Section 11(4)(b) (the promoter’s duty to obtain the OC/CC and make it available to allottees), Section 17 (conveyance and handover of possession), Section 19(10) (the allottee’s duty to take possession within two months of the occupancy certificate), and para 7.2 of the U.P. Real Estate (Regulation and Development) (Agreement for Sale/Lease) Rules, 2018, under which possession is offered in writing only after the OC/CC is obtained.
The conclusion was clear. Without an occupancy certificate, possession cannot lawfully be handed over and title cannot lawfully pass. Every fit-out offer, demand letter, reminder, final call letter and “pronouncement letter” issued without a legal or validly deemed OC/CC was declared illegal and not acceptable.
3. No Valid Demand Means No Default, So the Cancellations Fall
This is the heart of the ruling, and it was central to our case. Under the agreed payment plans, the large final instalment was payable on offer of possession. Measured against those plans, every allottee had already paid at least what was due before a lawful offer of possession, and some had paid well beyond it. The promoter admitted these payments in its own objections.
A buyer cannot default on an instalment that has not lawfully fallen due. Applying paras 9.2 and 9.3 of the 2018 Rules, the Authority held that the allottees committed no default, that the promoter itself breached the payment plan and the Act, and that the cancellations were illegal. It also noted that the promoter produced no evidence that third-party rights had been created in the units or that any refund had been made to and accepted by the allottees.
One more point stood out. The project’s OC was eventually obtained, as reflected on the RERA portal, but the promoter showed no fresh, lawful demand or possession offer issued after it. A later OC does not validate earlier invalid demands.
4. Delay Interest at MCLR + 1%, Calculated Even-Handedly
Under the proviso to Section 18(1), an allottee who stays in the project is entitled to interest for every month of delay until possession is handed over. The Authority:
excluded 68 days of Supreme Court-ordered construction bans in NCR (M.C. Mehta v. Union of India) as genuine force majeure;
treated the COVID window from 25.03.2020 to 25.09.2020 as neutral, so that neither side pays interest to the other for that period;
relying on M/s. Supertech Ltd. v. Rajni Goyal (Civil Appeal Nos. 6649–50 of 2018), ran interest until the legal OC/CC is obtained or a fresh valid possession offer with OC is issued, whichever is later;
fixed the rate at SBI MCLR + 1% under the 2018 Rules, noting that the Allahabad High Court upheld this rate in Rudra Buildwell Constructions Pvt. Ltd. v. Poonam Sood and Habitech Infrastructure Ltd. v. State of U.P.; and
applied Section 2(za), so the builder can charge the allottee no higher rate than it must itself pay.
5. Two Bonus Rulings Every Homebuyer Should Know
No TDS on delay interest. The promoter cannot deduct TDS by invoking the Income Tax Act from the delay interest awarded. The Bench treated the amount as a decretal, compensatory sum, drawing on the Bombay High Court’s view in Neelkamal Realtors Suburban Pvt. Ltd. v. Union of India, 2017 SCC OnLine Bom 9302, that interest under Section 18 is compensatory and not a penalty.
Section 13 breach invites penalty. Allotment letters were not executed and registered in the agreement-for-sale format notified by the UP Government. Section 13(1) bars a promoter from accepting more than ten per cent of the cost “without first entering into a written agreement for sale with such person and register the said agreement for sale”. The Authority found a violation and referred the matters to the Secretary, UP RERA, for penalty proceedings under Section 61.
Why This Ruling Matters Beyond One Project
The order sits squarely within settled Supreme Court law. In Debashis Sinha v. R.N.R. Enterprise (Civil Appeal No. 3343 of 2020, decided 09.02.2023), the Court held that possession offered without the required completion certificate is illegal and that a purchaser cannot be compelled to accept it. Dharmendra Sharma v. Agra Development Authority (2024 INSC 667) and Parsvnath Developers Ltd. v. Mohit Khirbat (Civil Appeal No. 5289 of 2022, decided 20.02.2026) reaffirmed that position, the latter holding that an offer lacking a valid OC is legally invalid and is in itself a deficiency in service. Samruddhi Co-operative Housing Society Ltd. v. Mumbai Mahalaxmi Construction (P) Ltd. (2022) 4 SCC 103 treats the failure to obtain an OC as a deficiency in service.
Section 11(5) of the Act adds a statutory guardrail:
“The promoter may cancel the allotment only in terms of the agreement for sale: Provided that the allottee may approach the Authority for relief, if he is aggrieved by such cancellation and such cancellation is not in accordance with the terms of the agreement for sale, unilateral and without any sufficient cause.”
The practical takeaway is direct: when the demand is invalid, the default is invalid, and the cancellation built on it falls with it. And because Newtech Promoters & Developers Pvt. Ltd. v. State of U.P. (2021 INSC 716) recognises the allottee’s Section 18 entitlements as unconditional, a builder cannot avoid delay interest by issuing paper offers of possession.
The Last Word: A Cancellation Is Only as Strong as the Certificate Behind It
There is a quiet symmetry in this order. The builder tried to treat the buyers’ unpaid instalment as the reason the relationship ended. The Authority looked one step earlier and asked why that instalment was demanded in the first place. Without an OC, the answer was: it should not have been.
RERA was meant to make the paper trail run both ways. In a flat cancellation by the builder, the paper that matters most is not the cancellation letter the buyer receives — it is the occupancy certificate the builder was supposed to obtain before writing it.
Quick FAQs
Can a builder cancel my flat if I refuse an offer of possession without occupancy certificate? Not on that ground alone. As this order shows, a demand or cancellation premised on an invalid offer is itself unlawful.
Is an “offer of fit-out” the same as an offer of possession? No. Without a legal OC/CC (or a deemed OC that is proved as per local law), it carries no legal consequence for the buyer.
Till when do I get delay interest? Till the OC/CC is obtained or a fresh legal possession offer is made, whichever is later.
Read Order:
Disclaimer: This article is for general information and does not constitute legal advice. Facts of individual cases differ, and the order discussed may be subject to appeal.