Mahalumxi Buildtech Ordered by UPRERA to Comply with Allotment Obligations in their Project "Migsun Kiaan" [Read Orders]

Updated: Oct 29
In a recent legal development, Mahalumxi Buildtech Consortium Pvt. Ltd. has been handed a decisive judgment by the Uttar Pradesh Real Estate Regulatory Authority, Gautam Buddha Nagar, in favor of a homebuyer from their project "Migsun Kiaan." The ruling outlines specific directives for Mahalumxi Buildtech to fulfill its contractual obligations promptly. Here's a detailed breakdown of the key aspects of the judgment.

The Dispute in Brief
The project, Migsun Kiaan in Ghaziabad, is developed by Mahalakshmi Buildtech Consortium Pvt. Ltd. and registered with UP RERA. The buyers had booked units under a 20:80 payment plan. They paid the first 20% upfront, and the remaining 80% was due when possession was offered. The allotment letter gave a fixed possession date, including a six-month grace period.
That date passed without any lawful handover. Instead, the buyers received an “Offer of Fit-Out” and demand letters that added late-payment penalties. They approached UP RERA under Section 31, asking for possession, delay interest and execution of the sale deed.
What UP RERA Decided in the Migsun Kiaan RERA Order
1. A fit-out offer without an OC is no offer at all.
UP RERA read Section 11(4)(b) of the Act together with Clause 7.2 of the U.P. RERA (Agreement for Sale/Lease) Rules, 2018. It held that possession can be offered in writing only after the OC/CC is obtained. On “deemed completion”, it examined Section 15-A of the U.P. Urban Planning and Development Act, 1973. That section deems a completion certificate granted only if the authority does not respond within three months of a proper completion notice. The promoter could not produce evidence of such a notice and had not filed all the required NOCs. The fit-out offer and the demand letters were therefore set aside.
2. An unexplained penalty cannot stand.
The authority checked the ledger. It found the buyer had paid one small amount a few days late, and that delay entitled the promoter to interest only on that amount, only for those few days. The larger lump-sum “delay penalty” had no stated basis or calculation, so it was quashed.
3. Delay interest at MCLR + 1%.
Relying on Section 18(1), the Bombay High Court’s decision in Neelkamal Realtors Suburban Pvt. Ltd. v. Union of India (W.P. No. 2737 of 2017), and two Allahabad High Court rulings that upheld the rate, UP RERA awarded delay interest at SBI’s MCLR + 1%. In Neelkamal, the High Court described this interest as compensation, not a penalty. Interest runs from the day after the promised possession date until the date the OC/CC is obtained or a lawful possession offer is made, whichever is later.
4. The same rate applies both ways.
Under Section 2(za)(i), a promoter can charge a defaulting buyer only the rate it would itself pay for its own default. If the promoter charged the buyer a higher rate, that amount must be recalculated at MCLR + 1%.
5. No TDS deduction.
Delay interest awarded by RERA is a decretal amount. The promoter cannot deduct TDS from it.
The promoter was directed to:
hand over physical possession with the OC/CC and all facilities promised in the allotment letter or BBA;
adjust the delay interest against the final dues, and refund any excess;
execute the sale deed;
all within 45 days. If it does not comply, the buyers can seek execution through the RERA portal, and the promoter faces action under Sections 38, 40 and 63 of the Act.
Why the Migsun Kiaan RERA Order Matters to You
If you have a unit in Migsun Kiaan, or in any delayed project in Ghaziabad or Noida, here is what this means for you:
Don’t pay just because a “fit-out” or “possession” letter arrives. Ask for the OC/CC first.
Check your ledger. Unexplained penalties can be challenged.
Your delay interest keeps running until there is a lawful offer backed by an OC.
You can stay in the project and still be compensated. You don’t have to choose between your home and your rights.
Your home is likely the biggest investment you will make, so don’t let a builder’s delay cost you twice. Contact S&D Legal Associates today for a consultation, and let us help you get your keys and the compensation the law gives you.
We will keep this page updated as more Migsun Kiaan RERA orders are passed. Bookmark it and check back.
FAQs:
Q1: What is the significance of possessing an Occupancy Certificate/Completion Certificate (OC/CC)?
A1: The OC/CC signifies that the construction project has been completed in compliance with all regulations, ensuring the property is fit for occupancy.
Q2: How is interest calculated on delayed payments under the RERA Act?
A2: As per the RERA Act, the interest rate is determined by adding one percent to the Marginal Cost of Funds Based Lending Rate (MCLR) prevailing in the State Bank of India for delayed payments by the allottee.
Q3: What legal actions can be taken in case of non-compliance by the builder?
A3: Non-compliance of an order passed by Real Estate Regulatory Authority (RERA) can lead to punitive measures under Section 63 of the Real Estate (Regulation and Development) Act, 2016, and enforcement through the RERA.
Q4: How can a homebuyer enforce the RERA order?
A4: In case of non-compliance, the homebuyer has the legal right to seek enforcement through the Real Estate Regulatory Authority (RERA) in accordance with the RERA Act provisions.
READ ORDER:

![Triumph in UPRERA: Justice Prevails for ATS Allure Allottees Seeking Delay Interest. [Read Orders]](https://static.wixstatic.com/media/908030_b0d392956e4c4d07b17a0c0ee9e12901~mv2.jpg/v1/fill/w_980,h_1020,al_c,q_85,usm_0.66_1.00_0.01,enc_avif,quality_auto/908030_b0d392956e4c4d07b17a0c0ee9e12901~mv2.jpg)

![UP RERA: ATS Allure to Ensure Delivery of Possession and Payment of Delay Interest. [Read Orders]](https://static.wixstatic.com/media/908030_203ef43e0d40407da64384ead2075130~mv2.png/v1/fill/w_980,h_1020,al_c,q_90,usm_0.66_1.00_0.01,enc_avif,quality_auto/908030_203ef43e0d40407da64384ead2075130~mv2.png)
Comments